Project Dashboard

Projects
Project Name Total Bugdet Amount ($) Phase Currently In Status Days Left (%) Complete
HS #6 - Chaparral High School $147,000,000 Construction On Schedule 489 58 % 
Killeen High School Renovation $99,000,000 Construction On Schedule 620 33 % 
East Ward / West Ward Consolidation $48,000,000 Construction Move-In 125 100 % 
Clifton Park / Bellaire ES Consolidation $35,000,000 Construction Move-In 125 100 % 
Pershing Park / Sugar Loaf ES Consolidation $35,000,000 Construction Open 125 100 % 
Elementary School #36 $40,000,000 Construction On Schedule 125 60 % 
ADA Renovations $14,770,000 Construction On Schedule 0 68 % 
Safety & Security Upgrades $5,230,000 Construction Ahead of Schedule 0 100 % 
2017
2018
2019
2020
2021
2022
2023
05/22/2018Total Days: 155308/22/2022
05/22/2018Total Days: 168412/31/2022
07/10/2018Total Days: 114008/23/2021
07/10/2018Total Days: 114008/23/2021
07/10/2018Total Days: 114008/23/2021
05/14/2019Total Days: 83208/23/2021
07/10/2018Total Days: 90601/01/2021
05/22/2018Total Days: 82208/21/2020
Bond Schedule
Download Bond Schedule
Budget($)

Spent($)

Spent(%)
HS #6 41.32%
KHS Reno 25.57%
EW/WW ES 63.00%
CP/B 66.93%
PP/SL ES 77.29%
ES #36 34.18%
ADA 60.41%
Safety 91.92%